The paving schedule for Milestone Road has CHANGED. Milestone Road is not being paved until next spring. The actual schedule is as follows:
September 14, 2009 through November 15, 2009
- Install drainage and leaching basin structures along road edge
- Cutting/trimming trees
- Installation of guard rail
- Excavation/repaving of bike path
Starting in March 2010 (weather permitting)
- Roadway milling (five days)
- Roadway paving (12 days)
Fall 2010
|